Phase 2 - Week 3
Have continued to work on the tool box and have most of the skin on the frame. Pictures will follow next week as the remainer will be completed over the weekend.
Finally ordered the second gas tank from Brian Asbury. When the truck arrived last year the second one was missing. He has a nice one which only needs to have the neck moved. Will also seal it. Pictures to follow when it's received.
Obtained a set of drawings for the radio mast and had the parts plasma-cut and then bent to shape with a brake. Pictures of the before and after are below.
Regards,