#1
|
|||
|
|||
|
Hi Chris
Yes we discussed cutting and doing a curve piece as you mentioned but in the end did the pie cuts and welding. We have now finished replacing the bottom angle iron. A jig is really needed when you start cutting out parts as the remainder becomes very floppy. See photos of the semi finished back wall. It has to go back in the jig to finish the reinforcement ribs and tack weld them in the proper spot. Cheers
__________________
Bob Carriere....B.T.B C15a Cab 11 Hammond, Ontario Canada |
|
#2
|
|||
|
|||
|
...and it originated froman enquiry from Herman.
It seems that the front bearing.... Hyatt 1206 is no longer available but NTN as a substitute that does not fit. The counter shaft is 38.mm the ID of the new substitute is 38.44 and loose/ I have ordered both the 1207 and the offending 1206 and await there arrival..... will go into town with the countershaft and try them there for size. The reverse gear shaft MUST BE driven from the front towards the back or the case will crack for sure. the front end of the shaft is cut semicircle and fits into a beefed up section that effectively keeps the shaft from spinning. The reverse gear rotates on that shaft supported on two brass sleeves/bushings. To remove the countershaft from the bottom of the case you need to hammer the visible end of the shaft at the rear towards the front..... that will push out the sheet metal cap that sit tight over the front 1206 bearing. The 1206 from bearing has an insert or bearing race that needs to be removed to fit over the shaft. The shaft measures just under the original 38mm and the OD of the insert is 38.44mm making for a loose fit.
__________________
Bob Carriere....B.T.B C15a Cab 11 Hammond, Ontario Canada |
|
#3
|
|||
|
|||
|
.....is not very helpful. One would need to call them for specifics on these two bearings.
Still determine to see if there IS a modern substitute that fits properly or start building up a reserve of these odd sizes. Bob C
__________________
Bob Carriere....B.T.B C15a Cab 11 Hammond, Ontario Canada |
|
#4
|
|||
|
|||
|
The original GM part number for the bearing of 142260 comes up on ebay a couple times.
As well, for cross reference purposes, here is a link to the NSN for subject bearing, along with other part numbers (and the code for the manufacturers) of the same bearing. http://www.dlis.dla.mil/webflis/pub/...4596&newpage=1 Some examples are: EMERSON POWER TRANSMISSION CORPORATION ROLLWAY BEARING pn UM1305B108 CNH INDUSTRIAL A18182 MERITOR 1228H268 or 2338N580 The NSN page also gives the GM part number of 7451442, which on ebay leads you to these: http://www.ebay.com/itm/GMC-roller-b...item1c4e05e032 The dimensions he gives are somewhat off, but they are a hyatt 1206, are in Quebec Canada, he has plenty, and they are $6 each. |
|
#5
|
||||
|
||||
|
Bob
I ended up sheeting the rear cab panel with 16g which was a little heavier than original and harder to work with. I believe 18 g is correct and will form nice to the contour if you roll weld and tack into place as you go.
__________________
3RD Echelon Wksp 1968 M274A5 Mule Baifield USMC 1966 M274A2 Mule BMY USMC 1966 M274A2 Mule BMY USMC 1958 M274 Mule Willys US Army 1970 M38A1 CDN3 70-08715 1 CSR 1943 Converto Airborne Trailer 1983 M1009 CUCV 1957 Triumph TRW 500cc RT-524, PRC-77s, and trucks and stuff and more stuff and and....... OMVA, MVPA, G503, Steel Soldiers |
|
#6
|
|||
|
|||
|
Now waiting for fair weather to do the sandblasting and skinning.
Will be using 18guage Chris as it is closer to the original 19 gauge. We plan on rolling the ends and will work to have a close fit during dry runs. When everything is ready we will be using the automotive metal glue. works great and give sufficient working time before final set. Edge will be rolled at the bottom using a bead roller. We have used the glue before on a cab 13 and it worked beautifully solid with no heat warpage. It also seals the space between the angle and the skin hopefully reducing chance for rust to form. Should last another 74 years!! Everything will get coated with POR 15, binding primer and 2 or 3 coats of OD. While waiting for more suitable weather we will be redoing the engine cover panels that have cancer near the floor area. This will give us a chance to make use of our pan box brake. Cheers
__________________
Bob Carriere....B.T.B C15a Cab 11 Hammond, Ontario Canada |
|
#7
|
|||
|
|||
|
Notwithstanding the miserable 7 nches of white fluff we got in the last 24 hours...... Grant and I worked on the cab 11 after we managed to blow some of the snow out of the driving area.
At this time of the year I have to take the snowblower tractor out of the barn to get the cab 11 stored out of the sea can and into the barn. Weather warmed up and at one point Lucifer was cranking so much heat we had the place up to 75F..... and worked in our shirt sleeves. The issue is to fit the engine cover back on the truck. Both side panels have been eaten away by rust so before cutting an welding new patches to the panels we need to clearly establish how long should the patch be at the bottom where it bolts to the floor. Fitting the engine cover panels after the nose panels are in place MAY be the wrong sequence. One step forward 3 steps back. Next Tuesday will remove the front external engine cover and see if we can coaxed a few more 1/8 or 3/16 of travel so the engine cover will fit best. First frustrating discovery.... the engine side panel will not fit with a 261 c.i. and the civilian road draft tube..... it hits the the captive nuts of the removable panel that gives access to the plug wires and dizzy. Luckily Grant had salvaged a CMP cab 13 very short draft tube with a threaded fitting for the PCV. Removing the draft tube in cramped quarters is a nightmare. I crawled underneath and using a cut off broom handle was able to tap the underside of the draft tube enough to loosen it. We installed the shorter model and gained considerable clearance. The shorter draft tube required a piece of 3/8 rubber hose to extend the metal PCV pipe. Next week we wil flare a new complete steel line for the PCV system. Next step backward. My dizzy is equipped with a Pertronix system and has the typical 261 tall dizzy cap and rotor. Now we realize that the cap is way too close to the engine cover. The apparent solution, yet to be applied, is to replace the tall modern cap and rotor with a shorter 216 cap and rotor...... we will gain over one inch of clearance. It is also obvious that the spark plug wires are one too long and will need to be shortened by quite a few inches. Also some 90 degree plug boots will be beneficial for cyl. no 6 and 3. Angled boots for the dizzy on about half the cyl. will also help routing the cable as short as possile and without touching the engine cover. Fortunately I bought a full large grocery bag of ignition wiring at a flea market so I can mix and match until get the right fit. Finally quite proud with having fitted almost perfectly the two sides and back panel of the engine cover..... and about to start/drive the cab 11 out of the barn..... the starter lever we had screwed off the starter stomper would not fit back on as it was about 3/8 below the oval hole. Reason.... as we assembled what will be a cab 11 1/2 due to all the mix and match panels salvaged from other trucks most being cab 12. Now I know why the original engine panel of my cab 11 had the starter hole all enlarged and beaten and twisted..... of course we choose a better panel and the darn hole is now too high. Part of the solution is when we have the external panels from the nose removed and the floor panels tweaked we may have enough clearance to fit the starter handle back on. We keep reminding ourselves of the wise words of Phil Waterman when he talked about re assembly of his cab 12......." assemble every cab panel loosely then drive it around so parts will shake themselves in place... " theb tighten the bolts. Boy was he rigth!!!!! Once we have the engine cover properly fitting, they will still need to be removed for welding the rust patches...... see how they fit..... removed to paint them and install some heat/sound insulation and re installed with proper machines screws and the finishing cup washer and yards of antisqueaking gasket material. For that matter ALL the front end cab panels will need final removal for proper machine screws and gasket material installation, touch up of all the scratches on the paint and a final readjustment of the valves ( one seems to be ticking more than needed) and to subsitute a 216 valve cover with proper 216 air filter instead of the existing 261 4 bolts modern GM cover...... it will better disguise the 261 as a 216....after all it the same digits just sequenced differently. On the bright side we drove it in low gear 4x4 in 2 feet of wet snow and at a fast idle and the wheels do not even spin...... front and rear axle gouging a nice round center furrow in the snow bordered by two herringbone tracks in the snow. One day..... one day it will be all done....... Just remember when they say a 261 will just bolt in a CMP they did not particularly meant a cab 11. Cheers
__________________
Bob Carriere....B.T.B C15a Cab 11 Hammond, Ontario Canada |
![]() |
| Thread Tools | |
| Display Modes | |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| 2014 at the Hammond Barn | RHClarke | The Restoration Forum | 63 | 01-01-15 22:50 |
| 2011 at the Hammond Barn | RHClarke | The Restoration Forum | 328 | 01-01-12 22:09 |
| 2009 at the Hammond Barn | RHClarke | The Restoration Forum | 322 | 02-01-10 17:05 |
| Hammond Barn Visit | Wpns 421 | The Softskin Forum | 1 | 15-12-09 04:17 |
| 2006 at the Hammond Barn | RHClarke | The Restoration Forum | 172 | 02-04-07 23:13 |